Academy
52-week curriculum Each week has one claim lesson as its spine and two to four supporting lessons. Quarter 3 is split into blocks for data centres, tunnels and railways, ports and offshore, and buildings and infrastructure. This is a draft; the order may change.
Educational content; not legal advice. In a real dispute, rely on your contract and your legal adviser.
Go to the academy topic index
Quarter 1 · Weeks 1–13 · Foundations: contract, building the programme, records Week 1
L01 The DNA of a Claim FDC01 The FIDIC family and risk allocation SAH01 Why records? "No record, no event" in claims and payments TB-00 Opening: the match sheet Week 2
L02 Possession, Access, Ground and Piling Risk FDC02 Parties, the Engineer's role and notice rules SAH02 The daily site report: weather, crews and plant, work done, obstructions, visitors Week 3
L03 Contract Map, Document Priority and Authority FDC03 Programme, progress and the extension-of-time mechanism PLN01 Work breakdown structure and activity definition (WBS, durations, calendars) Week 4
L04 Tender Assumptions, Qualifications and Clarifications PLN02 Logic links, lag/lead and constraints P6T-01 XER file structure and project selection Week 5
L05 Notice to Proceed, Permits and Mobilisation PLN03 Critical path and float (total/free) P6T-02 Calendars, work hours and duration units Week 6
L06 A Workable Baseline Programme PLN04 Resource- and cost-loaded baseline P6T-03 WBS and L2/L3/L4 programme levels TB-01 The lost first programme: the baseline Week 7
L07 Calendars, Logic and Milestones PLN05 Programme quality check (DCMA 14-point logic) P6T-04 Relationship types (FS/SS/FF/SF) and lag Week 8
L08 Total Float, Free Float and Milestones P6T-05 Forward/backward pass, float and critical path TB-02 Total float, free float and milestone behaviour Week 9
L09 Employer Data and Design Responsibility FDC04 Variations, measurement and valuation P6T-06 Constraints and the DCMA hard-constraint check Week 10
L10 Performance Obligations and Design Standards SAH03 Photo and evidence standards: date/location, before–after, naming P6T-07 Progress entry: percent, actual dates, remaining duration Week 11
L11 The Submittal Completeness Gate SAH04 Correspondence and notice discipline, reference numbers, deadlines PLN06 Importing an XER into The-SiteTeam, saving a baseline, submission and approval FDC06 Claims and disputes; tracking in The-SiteTeam Week 12
L12 Approval Delay and Decision-Ready Submissions SAH05 Site forms and inspection: question types, records of inspection, document register FDC05 Payments: interim statements, payment certificates, retention P6T-08 XER export and the round trip to P6 Week 13 Case week
L13 Long-Lead Procurement and Vendor Data SAH06 Site reports, forms, correspondence, mail commands and the document register in The-SiteTeam SAH07 Case: tender Q&A discipline (Nota van Inlichtingen, Spørsmål og svar, ProjNet Q&A) and the RFI register FDC07 Case: Europe's standard contracts versus FIDIC (NS 8407, ABT18, UAV-GC, YSE 1998, US FAR) PLN07 Case: an 18-month programme from a German school tender (GU) Quarter 2 · Weeks 14–26 · Practice: variations, updates, payment Week 14
L14 Trade Interfaces and Builder’s Work MSP01 Project setup, calendars and working hours PLN-01 BOQ reading wizard and column mapping Week 15
L15 Instructions, RFI Replies and Constructive Change MSP02 Task structure, WBS and summary tasks, duration types and effort-driven scheduling PLN-02 L2/L3/L4 by discipline and area breakdown HKD01 Contract types and payment mechanisms Week 16
L16 Notice Regimes, Time Bars and Actual Knowledge MSP03 Links, lag/lead, constraints and deadlines PLN-03 Productivity, crew cap and labour assumption Week 17
L17 Variation Valuation and Daywork HKD04 Change management and new unit rates MSP04 Resources, cost, levelling and overallocation PLN-04 L5 work steps and progress measurement Week 18
L18 Daily Records and Evidence Architecture UPD01 Data date and the update cycle MSP05 Baseline, progress entry, earned value fields (BCWS/BCWP/ACWP) and reports Week 19
L19 Progress Measurement and Programme Updates UPD02 Progress measurement methods UPD03 Actual dates, remaining duration and out-of-sequence progress TB-03 Progress measurement and programme updates Week 20
L20 Delay Events, Critical Path and EOT UPD04 Baseline versus current programme: detecting delay and the S-curve MSP06 Moving data between Microsoft Project and P6/XER (MPP/XML ↔ XER) PLN-09 From the programme to notice and EOT evidence Week 21
L21 Concurrency and Responsibility Windows EVM01 Budget, cost breakdown and control accounts PLN-05 Tender programme from a German LV (GAEB X83) TB-04 Concurrent delay and responsibility windows Week 22
L22 Mitigation, Resequencing and Acceleration EVM02 PV, EV and AC EVM03 Variances and indices (SV, CV, SPI, CPI) PLN-06 Basis of schedule (K5) and justified warnings Week 23
L23 Payment Notices, Set-Off and Retention HKD02 Preparing an interim payment: measurement, stage percentages and deductions HKD03 Price adjustment and escalation EVM04 Forecasts (EAC methods, ETC, VAC, TCPI) Week 24
L24 Payment Bonds, Performance Bonds and Subcontract Recovery HKD05 Subcontractor payments, purchase orders and the final account EVM05 Commitments, procurement and cash flow PLN-07 Facade package: fabrication, procurement and installation sequence Week 25 Case week
L25 Semester I Integrated Case Workshop UPD05 Structure of the monthly progress report UPD06 Updating, the report screen and distribution in The-SiteTeam HKD06 Payments, cost visibility, procurement and subcontractor documents in The-SiteTeam EVM06 EVM, S-curve and cost visibility in The-SiteTeam Week 26 Midterm
UPD07 Case: a Smithsonian 2 MW solar design-build, from tender programme to monthly update HKD07 Case: a Danish ABT18 technical building and a Dutch termijnstaat payment plan EVM07 Case: budget and earned value on a US federal design-build canopy job MSP07 Case: building the same small project in Microsoft Project and The-SiteTeam, with a DCMA check PLN-08 Monthly report: planned / actual / forecast PLN-10 Document control with ISO 19650: from drawing to claim evidence Quarter 3 · Weeks 27–39 · Sector blocks and delay analysis Week 27 Data centres
L26 Selecting the Delay Analysis Method P6I-01 Large master XER: multiple calendars, LOE and WBS summaries DC-1 Data-centre programme: L1–L5 commissioning and handover (in preparation) Week 28 Data centres
L27 As-Planned versus As-Built and Windows P6I-07 Engineering/procurement hold (EP) and expediting TB-05 As-planned versus as-built and windows DC-2 Long-lead equipment: generators, UPS, chillers (in preparation) Week 29 Data centres
L28 Time Impact Analysis and Fragnet Design P6I-02 K1–K5 rule check and basis of schedule EVM-01 Cost-loaded programme: BAC from BOQ amounts DC-3 Delay to the integrated systems test (IST) (in preparation) Week 30 Data centres
L29 As-Built Critical Path and Collapsed As-Built P6I-03 Driving chain and acceleration ideas TB-06 As-built critical path and collapsed as-built DC-4 Case: a delay file on an MEP-heavy project (in preparation) Week 31 Tunnels, roads and railways
L30 Programme Quality, Out-of-Sequence Progress and Manipulation P6I-04 Embedded DCMA 14 check: thresholds and fixes TB-07 Programme quality, out-of-sequence progress and critique of analysis quality TN-1 TBM/NATM progress and linear schedules (LOB) (in preparation) Week 32 Tunnels, roads and railways
L31 Disruption, Productivity and the Measured Mile P6I-05 Baselines inside the XER and the variance table EVM-02 Freezing the baseline TN-2 Differing ground and rings-per-day productivity (in preparation) Week 33 Tunnels, roads and railways
L32 Prolongation and Event-Based Cost P6I-06 Crew continuity levelling (K2) EVM-03 PV, EV, AC and the S-curve TN-3 Land acquisition, site possession and prolongation cost (in preparation) Week 34 Ports, shipyards and offshore
L33 Home Office Overhead and Eichleay P6I-08 Comparing two XERs: planned, actual, forecast EVM-04 SV/CV and SPI/CPI LM-1 Marine works: weather windows and standby (in preparation) Week 35 Ports, shipyards and offshore
L34 Global Claims and Responsible-Cause Deduction P6I-09 Programme and XER output from GAEB X83 EVM-05 EAC, ETC, VAC and TCPI methods LM-2 Heavy lifts and marine spread cost (in preparation) Week 36 Ports, shipyards and offshore
L35 Total Cost and Modified Total Cost EVM-06 Earned schedule: ES, SPI(t), forecast finish EVM-07 Progress payments and cash flow LM-3 Shipyard/offshore: block fabrication and change (in preparation) Week 37 Buildings and infrastructure
L36 Expert Independence and Report Architecture BIM01 What is IFC? Model structure, classes, property sets and base quantities BIM02 Quantities from the model: mapping templates, exclusions, units and base-quantity warnings TB-08 Expert independence and report architecture BN-1 Buildings: the façade package and interface claims (in preparation) Week 38 Buildings and infrastructure
L37 Cross-Examining the Delay Expert BIM03 BOQ structure and unit rates: pricing from a price list BIM04 Comparing model revisions TB-09 Cross-examining the delay expert BN-2 Infrastructure: existing utilities, excavation and diversions (in preparation) Week 39 Buildings and infrastructure Case week
L38 Cross-Examining the Quantum Expert BIM05 Managing coordination issues with BCF BIM06 BOQ revision comparison, cost impact and GAEB exchange BIM07 Case: from a GAEB bill to a BOQ and a revision comparison EVM-08 Period comparison and approved periods BN-3 Case: an integrated building and infrastructure file (in preparation) Quarter 4 · Weeks 40–52 · Completion, disputes and final exam Week 40
L39 Quality, ITP, NCR and Defect Management RSK01 Risk versus uncertainty; the risk register AIP-01 What is AI and what is not: engine and Gemini surfaces Week 41
L40 Testing, Commissioning and System Boundaries RSK02 Probability-impact matrix and heat map AIP-02 Rule-based programme from the BOQ and lessons learned Week 42
L41 Completion, Punch Lists and Practical Completion RSK03 Duration uncertainty: three-point estimates and distributions AIP-03 Reading contract clauses: rule table + Gemini Week 43
L42 Partial Possession, Sectional Completion and LD RSK04 Monte Carlo simulation, P50/P80, sensitivity and merge bias AIP-04 Reading a scanned contract page PBI-01 What Power BI does and does not do: loading the pack Week 44
L43 Suspension, Default and Cure RSK05 Interpreting results, contingency and risk actions AIP-05 Correspondence classification and RACI assignment PBI-02 The model: tables, relationships and several projects Week 45
L44 Termination and Post-Termination Damages RSK06 Risk board, heat map and the Monte Carlo screen in The-SiteTeam AIP-06 Draft reply: human approval and limits TB-10 Final: termination day, 4 June 2015 Week 46
L45 Performance Bonds and Surety Intervention RSK07 Case: USACE access shafts and a Norwegian sports hall — risk register and Monte Carlo from tender documents AIP-07 Polishing the claim narrative PBI-03 Project indicators as DAX measures Week 47
L46 Final Account, Release and Reservation of Rights AIP-08 Checking AI output with DCMA and the driving chain PMP01 Exam structure, eligibility and a study plan PBI-04 Dashboard design: executive, project manager, planner Week 48
L47 Limitation, Time Bars and Claim Survival AIP-09 Decision log and advance warning on site: report, decision, risk PMP02 People: team, conflict and stakeholder management PBI-05 Refresh, sharing and security Week 49
L48 Adjudication, Arbitration and Litigation Strategy PMP03 Process: scope, time and cost (CPM and EVM calculations) PMP04 Risk, quality, procurement and contracts Week 50
L49 Settlement, Mediation and Claim Cash Strategy PMP05 Agile and hybrid approaches in construction (look-ahead, Last Planner-style methods) PMP06 Business environment: governance, compliance, change and value Week 51 Capstone
L50 Capstone: Forensic Dossier, Expert Report and Hearing PMP07 Mock exam strategy and 20 original sample questions Week 52 Final
Final exam and year review Technical Office Engineering path · 108 hours Contract, programme, updates, payments and change management, in the order a technical-office engineer meets them on a project. Existing lessons brought together, ending in a graded project on the EPC Petrochemical Project programme and a certificate.
1 · 16 hours
Contract and record basics FDC01 The FIDIC family and risk allocation FDC02 Parties, the Engineer's role and notice rules L01 The DNA of a Claim L03 Contract Map, Document Priority and Authority SAH01 Why records? "No record, no event" in claims and payments SAH02 The daily site report: weather, crews and plant, work done, obstructions, visitors SAH03 Photo and evidence standards: date/location, before–after, naming SAH04 Correspondence and notice discipline, reference numbers, deadlines SAH05 Site forms and inspection: question types, records of inspection, document register 2 · 22 hours
Building the programme PLN01 Work breakdown structure and activity definition (WBS, durations, calendars) PLN02 Logic links, lag/lead and constraints PLN03 Critical path and float (total/free) PLN04 Resource- and cost-loaded baseline PLN05 Programme quality check (DCMA 14-point logic) PLN06 Importing an XER into The-SiteTeam, saving a baseline, submission and approval PLN07 Case: an 18-month programme from a German school tender (GU) L06 A Workable Baseline Programme L07 Calendars, Logic and Milestones L08 Total Float, Free Float and Milestones 3 · 16 hours
Updates and progress reporting UPD01 Data date and the update cycle UPD02 Progress measurement methods UPD03 Actual dates, remaining duration and out-of-sequence progress UPD04 Baseline versus current programme: detecting delay and the S-curve UPD05 Structure of the monthly progress report UPD06 Updating, the report screen and distribution in The-SiteTeam UPD07 Case: a Smithsonian 2 MW solar design-build, from tender programme to monthly update L19 Progress Measurement and Programme Updates 4 · 26 hours
Payments, cost and earned value HKD01 Contract types and payment mechanisms HKD02 Preparing an interim payment: measurement, stage percentages and deductions HKD03 Price adjustment and escalation HKD04 Change management and new unit rates HKD05 Subcontractor payments, purchase orders and the final account HKD06 Payments, cost visibility, procurement and subcontractor documents in The-SiteTeam HKD07 Case: a Danish ABT18 technical building and a Dutch termijnstaat payment plan EVM01 Budget, cost breakdown and control accounts EVM02 PV, EV and AC EVM03 Variances and indices (SV, CV, SPI, CPI) EVM04 Forecasts (EAC methods, ETC, VAC, TCPI) EVM05 Commitments, procurement and cash flow EVM06 EVM, S-curve and cost visibility in The-SiteTeam EVM07 Case: budget and earned value on a US federal design-build canopy job FDC05 Payments: interim statements, payment certificates, retention L23 Payment Notices, Set-Off and Retention 5 · 14 hours
Variations, notices and extension of time FDC03 Programme, progress and the extension-of-time mechanism FDC04 Variations, measurement and valuation FDC06 Claims and disputes; tracking in The-SiteTeam FDC07 Case: Europe's standard contracts versus FIDIC (NS 8407, ABT18, UAV-GC, YSE 1998, US FAR) L15 Instructions, RFI Replies and Constructive Change L16 Notice Regimes, Time Bars and Actual Knowledge L17 Variation Valuation and Daywork L18 Daily Records and Evidence Architecture L20 Delay Events, Critical Path and EOT 6 · 14 hours
Final project: one month on the EPC Petrochemical Project programme Prepare one monthly update, a payment application and an extension-of-time notice on the EPC Petrochemical Project programme; the instructor grades it.