Extra excavation instruction, ground improvement
weak 30/100 · Record window 2026-08-06 – 2026-10-15
- Notice compliance42/100 · weight 25%
- Contemporaneous records17/100 · weight 20%
- Programme linkage40/100 · weight 20%
- Causation and concurrency0/100 · weight 15%
- Quantum evidence0/100 · weight 12%
- Contract basis100/100 · weight 8%
Gaps and next steps
- missingNotice issued within the periodNotice compliance
The last day 2026-09-17 has passed; no notice on record.
What to do: Send and record the notice today; document the reason for the delay and the awareness date.
In the academy:L16 · Notice Regimes, Time Bars and Actual KnowledgeL47 · Limitation, Time Bars and Claim SurvivalObrascon Huarte Lain SA v HM Attorney General for Gibraltar (2014)Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No. 2) (2007)Panther Real Estate Development v Modern Executive Systems Contracting (2019) - partialDetailed claim within its periodNotice compliance
Open; last day 2026-11-12 (7 days).
What to do: Prepare and send the fully detailed claim (basis, records, time and money) within its period.
- missingCausation shownCausation and concurrency
No causation analysis.
What to do: Show with the programme how the event moved the critical path; an estimate of days is not enough.
- missingSite diary and field reportsContemporaneous records
0 days of site reports
What to do: Keep a daily site record over the event period: affected area, crew, plant, standing time and the obstacle.
- missingConcurrency examinedCausation and concurrency
Concurrency not examined.
What to do: Separate any contractor delay in the same period with a windows analysis and write it down.
- missingActual cost recordsQuantum evidence
No cost records.
What to do: Keep the event's actual costs (invoices, timesheets, hire) separately under an event code.
- missingLabour and plant recordsQuantum evidence
0 days of resource records
What to do: Record standing and working labour and plant day by day for the affected area.
- missingAffected activities identifiedProgramme linkage
0 activities picked
What to do: Pick the programme activities the event affects on the notice clock.
- missingProgramme update after the eventProgramme linkage
0 versions after the event
What to do: Record progress after the event and save a new programme version.
- missingTIA fragnet preparedProgramme linkage
No fragnet duration or activity link.
What to do: Enter the fragnet duration on the clock, link the activities and run the TIA preview with the programme.
- partialCorrespondence around the eventContemporaneous records
1 register items in the window
What to do: Put the event's letters (instruction, RFI, objection, reply) on the register; aim for at least 3.
- missingDated photographsContemporaneous records
No photographs in the window.
What to do: Attach dated, located photographs to the register or the daily report.
- missingMeeting minutesContemporaneous records
No minutes in the window.
What to do: Raise the event at a progress meeting and have it minuted.
- missingEarned value before and afterQuantum evidence
Before: no · after: no.
What to do: Approve earned-value periods (PV/EV/AC) before and after the event.
- missingNotice letter on the registerNotice compliance
No letter reference.
What to do: Upload the notice letter to the correspondence register and link it to the clock.
Claim lifecycle · 10 stages, 60 checks
8/60 checks done · 13%1. Capture the event · Spot the change or delay on the day it starts and put it on record.
Typical failure: The event is discussed on site but nobody writes it down; weeks later its date and source are disputed.
- openDate, place and source of the event (instruction, RFI reply, drawing revision, site condition) written in one line
Is there a line in the change/event log, with a document number?
- met (records)Awareness date recorded with its reason (when, who, from which document)
The notice period runs from this date; it needs a document behind it.
- openChecked that the event is not our own default, design error or risk
Compare with the contract's risk allocation and our own ITP/NCR records.
- openAuthority of the person who instructed the change verified (authority matrix)
If the instruction was oral, was written confirmation requested?
- openAffected bill items and programme activities flagged
Is there a list of activities linked to the event in the programme?
In the records: 0 activities picked
- openRough time and cost estimate made and an owner assigned
Did the estimate reach management; is the file owner named?
In the academy:L01 · The DNA of a Claim
This checklist is not legal advice. The checks describe a disciplined record; they do not predict the outcome of a claim. Check clause numbers and periods against your own contract and with a lawyer.
This score is not legal advice. It measures the state of the records on file; it does not predict the outcome of a dispute. Check periods and clauses against the contract and with a lawyer.