Sample project — fictional data

From bill of quantities to programme, no sign-in needed

This page turns a sample office building bill of quantities (19 items, 2 blocks) into a programme in your browser. No account is needed and no data is sent to a server. Progress and actual cost are fictional.

Reading the sample bill of quantities and building the programme…

Claim evidence score

The state of the records for each open claim: notice, contemporaneous records, programme linkage, causation, quantum evidence and the contract basis. Every gap shows the next step and the academy lesson and court decision behind it.

Sample project: three fictional claims. Your own file is scored on the claim page.

Claim portfolio (riskiest first)

ClaimScoreRatingNotice clockMain gap
2026-08-2030/100weakoverdue · 49 days overmissing: Notice issued within the period
2026-10-0166/100fairdue soon · 0 days leftpartial: Notice issued within the period
2026-09-1096/100strongon track · 28 days leftpartial: Detailed claim within its period

Extra excavation instruction, ground improvement

weak 30/100 · Record window 2026-08-06 – 2026-10-15

Pillar scores
  • Notice compliance42/100 · weight 25%
  • Contemporaneous records17/100 · weight 20%
  • Programme linkage40/100 · weight 20%
  • Causation and concurrency0/100 · weight 15%
  • Quantum evidence0/100 · weight 12%
  • Contract basis100/100 · weight 8%

Gaps and next steps

  1. missingNotice issued within the periodNotice compliance

    The last day 2026-09-17 has passed; no notice on record.

    What to do: Send and record the notice today; document the reason for the delay and the awareness date.

  2. partialDetailed claim within its periodNotice compliance

    Open; last day 2026-11-12 (7 days).

    What to do: Prepare and send the fully detailed claim (basis, records, time and money) within its period.

  3. missingCausation shownCausation and concurrency

    No causation analysis.

    What to do: Show with the programme how the event moved the critical path; an estimate of days is not enough.

  4. missingSite diary and field reportsContemporaneous records

    0 days of site reports

    What to do: Keep a daily site record over the event period: affected area, crew, plant, standing time and the obstacle.

  5. missingConcurrency examinedCausation and concurrency

    Concurrency not examined.

    What to do: Separate any contractor delay in the same period with a windows analysis and write it down.

  6. missingActual cost recordsQuantum evidence

    No cost records.

    What to do: Keep the event's actual costs (invoices, timesheets, hire) separately under an event code.

  7. missingLabour and plant recordsQuantum evidence

    0 days of resource records

    What to do: Record standing and working labour and plant day by day for the affected area.

  8. missingAffected activities identifiedProgramme linkage

    0 activities picked

    What to do: Pick the programme activities the event affects on the notice clock.

  9. missingProgramme update after the eventProgramme linkage

    0 versions after the event

    What to do: Record progress after the event and save a new programme version.

  10. missingTIA fragnet preparedProgramme linkage

    No fragnet duration or activity link.

    What to do: Enter the fragnet duration on the clock, link the activities and run the TIA preview with the programme.

  11. partialCorrespondence around the eventContemporaneous records

    1 register items in the window

    What to do: Put the event's letters (instruction, RFI, objection, reply) on the register; aim for at least 3.

  12. missingDated photographsContemporaneous records

    No photographs in the window.

    What to do: Attach dated, located photographs to the register or the daily report.

  13. missingMeeting minutesContemporaneous records

    No minutes in the window.

    What to do: Raise the event at a progress meeting and have it minuted.

  14. missingEarned value before and afterQuantum evidence

    Before: no · after: no.

    What to do: Approve earned-value periods (PV/EV/AC) before and after the event.

  15. missingNotice letter on the registerNotice compliance

    No letter reference.

    What to do: Upload the notice letter to the correspondence register and link it to the clock.

Claim lifecycle · 10 stages, 60 checks

8/60 checks done · 13%

1. Capture the event · Spot the change or delay on the day it starts and put it on record.

Typical failure: The event is discussed on site but nobody writes it down; weeks later its date and source are disputed.

  1. openDate, place and source of the event (instruction, RFI reply, drawing revision, site condition) written in one line

    Is there a line in the change/event log, with a document number?

  2. met (records)Awareness date recorded with its reason (when, who, from which document)

    The notice period runs from this date; it needs a document behind it.

  3. openChecked that the event is not our own default, design error or risk

    Compare with the contract's risk allocation and our own ITP/NCR records.

  4. openAuthority of the person who instructed the change verified (authority matrix)

    If the instruction was oral, was written confirmation requested?

  5. openAffected bill items and programme activities flagged

    Is there a list of activities linked to the event in the programme?

    In the records: 0 activities picked

  6. openRough time and cost estimate made and an owner assigned

    Did the estimate reach management; is the file owner named?

Weights: notice 25%, records 20%, programme 20%, causation 15%, quantum 12%, contract 8%. Method: docs/claim-evidence-score.md.

Try it with your own bill of quantities

Use the same programme, checks and exports with your own budget Excel free of charge until 31 March 2027.